1/7 < >

Interim Busgates Fraport, Frankfurt

New Building, Hall

Owner: Fraport AG, Frankfurt
Architect: Menzel & Kossowski, Darmstadt

Performance: Structural Design
Work Phases: 1-6
Total Area: 2.800 m²

Completion: 2007

For the temporary evacuation of a bus-gate at Frankfurt Airport osd developed a lightweight steel roof support. The steel truss girders span the whole room without additional support. Using a framework the necessary height of the construction could be used for the installation of building services.

Exterior (photo Mark Brom)

Foto

Exterior (photo Mark Brom)

Foto

Interior (photo Mark Brom)

Foto

Interior (photo Mark Brom)

Foto

Roof support with truss girders (photo Mark Brom)

Foto

Exterior by night (photo Mark Brom)

Foto

Exterior by night (photo Mark Brom)

Foto